What this calculator does – and what it will not do
It answers one question: given holes of this size, how much concrete do I need to buy? It does the volume arithmetic carefully and shows every step.
It does not tell you how deep or how wide the holes should be. The right footing depends on frost depth, soil, fence height, wind exposure, the post product and your local building requirements. No field on this page is derived from any of those. Get the dimensions from your installer, the fence manufacturer’s instructions or your building department, then enter them here.
The formula
Each hole is treated as a straight vertical cylinder and each post as round.
concrete depth = hole depth − gravel depth hole volume = π ÷ 4 × hole diameter² × concrete depth ÷ 1,728 (cu ft) post volume = π ÷ 4 × post diameter² × embedded length ÷ 1,728 (optional) per hole = hole volume − post volume all holes = per hole × number of posts with waste = all holes × (1 + waste %) bags = with waste ÷ yield per bag, rounded up
Dimensions are in inches; dividing by 1,728 converts cubic inches to cubic feet. The embedded length used for the post is capped at the concrete depth, because a post cannot displace concrete below the bottom of the pour.
Worked example
Four holes, each 10 in across with 24 in of concrete, around a 2 in round post set the full depth:
- Hole: π ÷ 4 × 10² × 24 ÷ 1,728 = 1.0908 cu ft
- Post: π ÷ 4 × 2² × 24 ÷ 1,728 = 0.0436 cu ft
- Per hole: 1.0908 − 0.0436 = 1.0472 cu ft
- Four holes: 4.1888 cu ft
- With a product that yields 0.60 cu ft per bag: 4.1888 ÷ 0.60 = 6.98, so 7 bags
- With a 10% waste allowance: 4.6077 ÷ 0.60 = 7.68, so 8 bags
Notice what happens if you round up for each hole instead: one hole needs 1.75 bags, which rounds to 2, and four holes would be 8 bags before any waste. Rounding once for the whole job avoids buying concrete you will not use, which is why the waste allowance is a separate, visible choice.
Bag yields
A bag’s yield is the volume of mixed concrete it makes. It is set by the product, not only by the bag’s weight, so two 80 lb bags from different product lines can differ. The calculator includes one labeled reference product; for anything else, choose “Another product” and type the yield printed on the bag or its data sheet.
| Bag weight | Approximate yield |
|---|---|
| 40 lb | 0.3 cu ft |
| 50 lb | 0.375 cu ft |
| 60 lb | 0.45 cu ft |
| 80 lb | 0.6 cu ft |
| 90 lb | 0.675 cu ft |
Source: QUIKRETE® Concrete Mix (No. 1101) product data sheet (data sheet marked “Revised October 2022”). These figures apply to that product only. Fast-setting mixes and other brands publish their own yields. Manufacturers revise data sheets, so check the bag in front of you.
What you need to enter
- Number of posts – taken from your saved fence layout, or typed in directly.
- Hole diameter and depth – as specified for your fence and location.
- Gravel depth – if you put drainage gravel in the bottom of the hole. Gravel is reported separately and is not concrete.
- Post diameter – only matters if you choose to subtract the post’s volume.
- Bag yield – from the reference list or from your product.
- Waste allowance – your margin for spillage and holes that are wider than planned.
Assumptions and limits
- Holes are perfect cylinders. Hand-dug and augered holes are usually irregular and often belled, so real volume tends to be higher. That is what the waste allowance is for.
- Posts are round. For a square post either leave “subtract the post” off, or enter the diameter of a circle with the same area (side × 1.128).
- All holes of a type are the same size. You can give line, end, corner and gate posts different holes.
- The result is a quantity to buy, not a mix design or a statement that a footing is adequate.
- Some fence systems and some installers set posts without concrete at all. Whether to use it is outside this calculator.
Common mistakes
- Using the hole depth as the concrete depth when there is gravel in the bottom. Six inches of gravel in a 30 in hole leaves 24 in of concrete.
- Mixing up radius and diameter. The formula here uses diameter – the full width of the hole.
- Rounding bags per hole. It can add a bag or more on even a small job.
- Assuming every 80 lb bag yields the same. Check the product’s stated yield.
- Forgetting gate posts. A gate adds two posts, and they are often set in larger holes than line posts.
References
- Calculation methods and sources – grouping, rounding and validation rules in full.